As found in FCC Final Rule Part 1, Subpart U, Section 1.6003 (d), City staff shall
review for completeness any permit application to deploy small wireless communications
facilities, and shall notify the applicant on or before the tenth (10
th
) day after submission if the application is materially incomplete, and shall clearly
and specifically identify the missing document or information, and the specific rule
or regulation requiring such document or information. The ten-day limit (above) shall
restart at zero on the date on which the applicant submits all the documents and information
identified by City staff to render the application complete. As required by Section
36-504.D.7. of the State Act, an application shall be processed on a nondiscriminatory
basis and deemed approved if the City fails to approve or deny the application within
seventy-five (75) days of receipt of the application. Upon issuance of a City permit,
a small wireless communications provider shall install its facilities and commence
operation within one (1) year, as explained in subsection D. of Section 36-504, paragraphs
5 and 11.
(Ord. No.
24060
, § 1, 12-5-2018)
var val = document.getElementById('citecontent').innerHTML;
art.dialog.defaults.title = window.location.href;
art.dialog.data('cite', val);
art.dialog.data('homeDemoPath', '/Scripts/plus/artDialog/');
art.dialog.open('/Scripts/plus/artDialog/citeiframe.html');